REQUIREMENT
A new container terminal is under construction at the port of Naples, located at the “Darsena di Levante” eastern dock. From an operational poin of view, the project has to face major environmental and construction challenges, due to the position on the sea.

SOLUTION
SIMEM supplied a MMX 5000: an extremely mobile plant thanks to several innovations and patented features applied on it. Cement silos are also mobile as they are equipped with own legs that avoid the construction of concrete pillars to support them and allow a quick removal after completing the job. A twin-shaft mixer produces 3.33 m3 of compacted concrete per batch that means 130 m3 per hour in 40 cycles.
The plant is also equipped with a Betonwash to clean and recover slurry water.